TSNPDCL LT NEW CONNECTION DASHBOARD
 

Registration From Circle: Category: Purpose Of Supply From Date: To Date :    
 
 
Abstract Report(Except Category V) : TSNPDCL


Application Status

No.of Application Received 3313
Additional Data Required 65
Feasibility Status

Pending for Issue of Feasibility 13
Feasibility Issued 3057
Non-Feasible(Rejected) 176

Estimate Status

Estimate Required 1305
Estimate Not Required 1752
Estimate Sanction Status
(Estimate Required Only)

Pending for Sanction 427
Sanctioned 861
Rejected 17
Demand Status
(Estimate Required Only)

Demand Notice Pending 27
Demand Notice Issued 834
Payment Status
(Estimate Required & Estimate Not Required)

  Not Required Required Total
Payment Pending 183 181 364
Payment Received 1569 653 2222
Work Status
(Estimate Required Only)

Work To be Taken Up 292
Additional Payment Pending 8
Work Under Progress 79
Work Completed 276
CEIG Approval Status
(Estimate Required Only)

CEIG Approval Pending 21
CEIG Approval Not Required 250
CEIG Approval Received 2
Release Status
(Estimate Required & Estimate Not Required)

  Not Required Required Total
Release Pending 41 37 78
Services Released 1528 216 1744